Subscribe

RSS Feed (xml)

Powered By

Skin Design:
Free Blogger Skins

Powered by Blogger

Saturday, May 2, 2009

Aggregate POC Calculation

When we confirm activities and see it in cns41 report we can see that the POC is aggregated at the Network,WBS and porject level. How does the system calculate this.. i.e on what factors and criteria?

Result analysis determines the costs & revenues belong to the period, along with the Work in progress (WIP) or Reserves.

Result analysis calculation is based on the planned / actual Cost & Revenue.

POC (Percentage of Completion) determines by the valuation method you opt …

The formula for POC :

POC = R (a) / R (P) Revenue Proportionate

POC = C (a) / C (p) Cost Proportionate

Result Analysis Determines:

- Calculated Costs C(c) = POC X C (p) Same for Revenue
- WIP (If C(a) >C (c) ) WIP = C(z)= C(a) - C(p)
- Reserves for unrealized costs (if C(a) <> R(c) )
R (r) = R(a) –R(c)

E.g.

Revenue Proportionate RA:

In some project you have R(p) =3000$
C (p) = 2000$
R (a) = 1200$
C (a) = 1000$

Then POC = 1200 /3000 = 40 %

C(c) = POC X C(p) = 40 % X 2000 = 800$

WIP = C(z) = C(a) –C(c) = 1000-800 =200$



Related Topics:

SAP LIS - Wrong figures in Logistics Information System
List of standard Reports in MM
Project Status set to TECO
List of RA caculated values
Stop Commitments Before Release Of Projects
What is WBS element?
Aggregate POC Calculation
Dynamic Selection on Report Not Working

Bookmark and Share

No comments:

Post a Comment

Archives