Q: How to configure the planning calendar for the ATP calculation where goods are shipped every other working day?
Use Transaction MD25 and define calculation rule for every other working day.
Check the lot size settings in OMI4 and maintain relevant data in MMR.
Q: We have two different production lines with different operations. One production line works 5 days a week and the other 7 days a week. The factory calendar is assigned to the plant for 5 days a week. This calendar is checked when MRP is run. How can we assign 5 day a week and 7 days a week against a factory calendar to the related resources? Is it possible to have two types of calendars?
A: Assign factory calendars to the work centers.
Q: What is the difference between by-product and co-product and how do you differentiate them in a BOM?
A: In case of Co-product costs are settled with a apportionment structure. In case
of By-product the price of this by-product is credited to the order or the material
stock account of the lead material being manufactured.
Co-Product as well as by-product are defined as BOM Components/Items. Both of
them have negative quantities. ( Not all negative quantity items fall under these
categories!). When BOM is created for FERT , you
can see one indicator in COMPONENT DETAILS screen for co-product. You need
to define the co-products with this special indicator .
Q: What are some important tables used in PP ?
A: For orders:
CUAFVD dialog structure for order headers and items
AFPO - Order item
AFFLD Order: Dialog table for order sequences (AFFL)
MOPER Operation for production order
KBED Capacity requirements
AFRU Order completion confirmations
RESB Reservation/Dependent Requirements
AFFHD Structure of PRT's in orders
SOPER Sub-operations
SAFRU Sub-operation confirmations
SKBED Capacity requirements for sub-operation
MRP table is MDTB.
For PI:
CAUFV - AFVC Operation within an order
AFFT Order Process Instructions
AFFV Order process instruction values
Monday, September 7, 2009
Subscribe to:
Post Comments (Atom)
Archives
-
▼
2009
(413)
-
▼
September
(36)
- PP MRP Calculation to determine the delivery date ...
- PP MRP Purchasing processing Time - OPPQ
- PP MRP Define Safety Stock Availability
- PP MRP Questions on MRP Group and MRP Controller
- PP MRP Planning separately via Storage Location or...
- PP - The Common Planning Strategy used
- PP MRP Why Planning file entry still Exists?
- PP MRP Planning Strategy Selection
- PP MRP Monthly lot size
- PP MRP Reservation Not Created During MRP Run
- PP MRP How to Configure Range Of Coverage Profile
- PP MRP Lose of link between sales order and produc...
- PP Batch Characteristics while Running MRP
- PP What is Firming Type in the MRP Types
- PP MRP Functions of Production Version
- PP MRP What is Discrete Manufacturing, REM and Dem...
- PP MRP Discrete Manufacturing - The Made To Order ...
- PP MRP Discrete Manufacturing - The Made To Stock ...
- PP MRP Discrete Manufacturing - The Step By Step T...
- PP MRP Steps To Do Repetative Manufacturing
- PP Message / System Status Changing warning msgs t...
- Production Planning - Production Control System Me...
- PP Message / System Status Production Order System...
- Explain System and User Status In Production Order
- SAP PP Certification Sample Questions I
- SAP PP Self Test Certification Questions
- SAP PP Questions and Answers II
- Sample Questions on SAP PP
- SAP PP Test Questions MCQ
- Interview Questions and Anwsers on SAP PP
- PP Interview Questions Year End To Do List
- SAP Production Planning and Control Frequently Ask...
- List of PP Transport Request and their IMG Path
- The Overall Flow For SAP PP
- Planning & Production Alternate Plant
- PP Interview Questions I
-
▼
September
(36)
No comments:
Post a Comment