Subscribe

RSS Feed (xml)

Powered By

Skin Design:
Free Blogger Skins

Powered by Blogger

Monday, September 7, 2009

SAP PP Self Test Certification Questions

1. Following are valid BOM categories

a) Inspection BOM
b) Material BOM
c) Equipment BOM
d) Costing BOM

Ans : b, c, d

2. Material BOM that is created without plant is called______________

a) Reference BOM
b) Master BOM
c) Group BOM
d) Master group

Ans: c

3. If a Header Material is used as a BOM item in the same BOM the BOM is referred as ___

a) Repetitive BOM
b) Alternative BOM
c) Multiple BOM
d) Flexible BOM
e) Recursive BOM

Ans:

4. Alternative BOMs are grouped under one internal number and are called__________

a) Multiple BOM
b) Variant BOM
c) Variable BOM
d) Super BOM
e) Header BOM

Ans:

5. BOM can be used for the following

a) MRP
b) Costing
c) Inspection data
d) Sales & Distribution

Ans: a, b, c, d

6. The base quantity in the BOM specifies

a) To which amount of the semi finished product the item quantities refer
b) To which amount the item quantities required for two or more finished products
c) To which amount of the finished product the item quantities refer
d) To which amount the item quantities are not calculated.

Ans: a, b, c

7. Work Center is used in

a) Routing
b) BOM
c) Material Master
d) Inspection Plans

Ans: a, d

8. Routing contains information on the following

a) Material Components
b) Operations
c) Capacity for Work Centers
d) Inspection Characteristics

Ans: a, b, c

9. Alternative sequences in routing are created with reference to

a) Parallel Sequence
b) Master Sequence
c) Standard Sequence
d) Reference Sequence

Ans:

10. Work Center requires formulas for the following

a) Move time
b) Scheduling
c) Capacity requirements
d) Cost estimate using activities

Ans:

11. Routings are identified by ____________________

a) Routing Group
b) Routing Status
c) Group Counter Values
d) Routing Group and Group Counter Values
e) Status and use

Ans:

12. You can assign work center to only one cost center in a time period.

a) True b) False

Ans:

13. Production Planning Module is integrated with the following modules.

a) Material Management
b) Controlling
c) Quality Management
d) Sales & Distribution

Ans: a, b, c, d

14. Movement Type for Goods Receipt in to Ware House

a) 122 b) 123 c) 101 d) 102

Ans: c

15. Movement Type for Transfer Posting to storage location

a) 261 b) 301 c) 311 d) 305

Ans: c