Repetative manufacturing is period based planning and not based on orders. Normally same products will be manufactured over longer period of time..products will not change frequently. Confirmation is from backflushing and settlement is through from product cost collector for the period. Confirmaton will be without ref to planned orders. Planned orders are sufficient to carry out shop floor activity. In master data production versions and cost collector is must where this is not mandatory in discreate.

You do these steps for rem production:

mm01 : Material Master
- MRP - 4 view you click rem

cs01 : Create Bom

cr01 : Create Work Center

ca21 : Create Rate Routing

mm02 : Prodn Version

md61 : Create PIR

mc74 : Transfer PIR to Demand

kkf6n : Create Product Cost Collector

mb1c : Create Stock

md02 : MRP run

mfbf : Rem Back Flush

The detailed sequence of T.Codes for REM including Std cost estimate.

Material master - MM01

BOM - CS01

Price Planning - KP26

Work Center - CR01

Rate Routing - CA21

Material Master Change, enter production version - MM02 (MRP 4 View)

Product Cost Collector - KKF6N

Costing - CK40N

Backflushing - MFBF